Construction Update

G.A.T.O Tower Key Construction Milestone

Read the G.A.T.O Tower construction update for September 2026. See the latest progress on concrete platforms, guide walls and jet grouting works in BKK1.

Share this Article

G.A.T.O Tower Construction Update: Foundation Works Progress in BKK1

Construction at G.A.T.O Tower continues to move forward in BKK1, Phnom Penh,

with several important milestones achieved in the project’s early foundation works.

The latest G.A.T.O Tower construction progress for October 2026 confirms that jet grouting for soil improvement, diaphragm wall guide wall construction, and the concrete working platform have all reached 100% completion.

Meanwhile, foundation testing preparations are progressing, with concrete casting completed for the P2 test pile and drilling and reinforcement fabrication underway for the P1 test pile.

These developments mark another important stage in preparing the site for the 67-storey mixed-use tower.

Read more: G.A.T.O Tower Developer Profile

October 2026 Construction Milestones

The latest construction update highlights the completion of three major site preparation activities, alongside continued progress on foundation testing piles and the delivery of reinforcement materials for diaphragm wall construction.

Jet Grouting for Soil Improvement – 100% Completed

Jet grouting injection works have reached 100% completion, marking an important milestone in the project’s ground improvement programme.

Jet grouting involves injecting grout into the ground under high pressure to strengthen and stabilize the existing soil. This process helps improve ground conditions for subsequent foundation construction.

With these works completed, G.A.T.O Tower has finalized one of its essential early-stage soil improvement activities.

Diaphragm Wall Guide Wall – 100% Completed

Construction of the retaining guide wall for the diaphragm wall has also reached 100% completion.

The guide wall helps establish the correct alignment for diaphragm wall excavation and provides guidance for construction equipment during the excavation process.

Its completion represents another important preparatory step for the project’s below-ground construction.

Concrete Working Platform – 100% Completed

The concrete working platform for heavy construction equipment and machinery is now 100% complete.

This platform provides a prepared surface for heavy machinery used during foundation construction, including equipment involved in drilling and excavation activities.

With the platform completed, another major component of the project’s site preparation works has been finalized.

Foundation Testing Pile Progress

Alongside the completed site preparation activities, construction teams are continuing work on two test piles designed for different load-testing purposes.

P2 Test Pile (D1800mm) – Concrete Casting Completed

Concrete casting for the P2 test pile, measuring 1,800mm in diameter, has reached 100% completion.

The P2 pile is designated for a working load test, which assesses how the pile performs under applied loads.

The completion of concrete casting marks an important construction milestone for this test pile, although the working load test itself has not yet been reported as completed.

P1 Test Pile (D2200mm) – Drilling and Reinforcement Underway

Construction is also progressing on the P1 test pile, measuring 2,200mm in diameter, which is designated for an ultimate load test.

According to the October 2026 update, two activities remain underway:

  • Drilling works: 30% completed
  • Rebar fabrication: 25% completed

Drilling prepares the bore for the test pile, while reinforcement fabrication involves preparing the steel reinforcement required for its construction.

Both activities are progressing as part of the project’s foundation testing preparations.

Diaphragm Wall Reinforcement Materials Delivered

The latest update also confirms the delivery of reinforcement steel for diaphragm wall construction.

These materials will be used during subsequent diaphragm wall works, which form an important part of the project’s below-ground construction.

The delivery follows the completion of the diaphragm wall guide wall and concrete working platform, marking continued preparation for the next stages of construction.

G.A.T.O Tower Construction Progress Summary – October 2026

Construction ActivityProgress
Jet grouting injection for soil improvement100% completed
Retaining guide wall for diaphragm wall100% completed
Concrete working platform for heavy equipment100% completed
P2 test pile (D1800mm) – concrete casting100% completed
P1 test pile (D2200mm) – rebar fabrication25% completed
P1 test pile (D2200mm) – drilling30% completed
Diaphragm wall reinforcementRebar delivered to site