Follow the latest construction progress at Kingston Royale as the residential tower continues advancing on schedule. Explore key milestones, ongoing site updates, and the development's journey toward its highly anticipated completion.
Home » News » Kingston Royale Condo Key Construction Milestone
Construction at Kingston Royale condominium continues to advance rapidly, hitting critical structural milestones as the tower rises above the Phnom Penh skyline.
As of end of July 2026, the project has reached another stage of structural development, with construction progressing according to schedule and multiple work fronts advancing simultaneously.
Current Construction Progress
Kingston Royale continues to make steady progress across both structural and building services works. Current site activities include:
16th Floor Concrete Pouring Underway
Concrete pouring for the 16th floor is currently in progress, demonstrating the project’s consistent vertical advancement and maintaining its planned construction timeline.
MEP Installation Progressing
Mechanical, Electrical & Plumbing (MEP) installation is actively underway from the 2nd to the 11th floor, ensuring essential building systems are installed in parallel with structural works to support efficient project delivery.
Internal Works Set to Begin
Next month, wall brickwork will commence, marking the start of the building’s internal partitioning works. This represents an important transition from structural construction toward interior development.
Construction Remains on Schedule
With structural, MEP, and upcoming masonry works progressing simultaneously, Kingston Royale continues to move forward according to schedule, bringing the development one step closer to completion.
Major Project Timeline
Kingston Royale has maintained a consistent construction pace since groundbreaking, achieving key milestones throughout its development.
Timeline
Milestone
August 2025
Construction commenced with basement excavation, reinforcement works, and foundation development.
January 2026
Basement and underground parking structures were completed, allowing above-ground construction to begin.
April 2026
The tower reached the 5th floor, marking steady progress under strict quality control standards.
June 2026
Structural works surpassed the 10th floor, with construction averaging nearly one floor per week.
July 2026
The project completed the 14th floor structural milestone, preparing for continued vertical expansion.
End of July 2026
Concrete pouring for the 16th floor is underway, MEP installation has progressed through Floors 2–11, and wall brickwork is scheduled to begin next month, marking the transition into internal partitioning works.
Project Details: Contemporary Urban Living
Designed as a premier 36-storey residential landmark in Boeung Tompun, Kingston Royale blends modern, affordable sophistication with highly efficient urban utility.
Scale and Scope: The development rises 36 storeys high and features a curated community of 310 units, with an optimized layout of 11 units per floor.
High-Yield Residences: The project prioritizes high-liquidity 1-bedroom and 2-bedroom configurations. These formats are the “bread and butter” of the Phnom Penh rental market, easy to manage, fast to rent out, and highly sought after for resale. Every unit features a generous 2.8-meter ceiling height designed to maximize natural light and ventilation.
Premium Amenities: Residents will enjoy full lifestyle infrastructure to attract high-quality tenants. This includes a ground-floor lobby and mini-mart, 7 dedicated floors of secure car parking with vehicle lift access, and a 33rd-floor wellness hub featuring a gym, steam room, sauna, jacuzzi, and yoga space. The building is topped by a rooftop sky sanctuary with an infinity pool and a scenic sky garden.
Because real estate appreciation is intrinsically linked to construction milestones, early investors who secured units prior to the structural ascendance are already benefiting from locked-in equity growth. With the building successfully reaching its 14th floor, the development continues to demonstrate substantial long-term value for both future residents and buy-to-let investors aiming for consistent 7–10% annual rental yields.
Contact us to book a viewing or inquire about remaining units today: