CONSTRUCTION UPDATE • SEPTEMBER 2026

ODOM Key Construction Milestone

Follow the latest construction progress at ODOM as both ODOM Living and ODOM Tower continue advancing on schedule. Explore key milestones, monthly site updates, and the development's journey toward its planned 2027 completion.

The latest ODOM construction progress shows significant advancement across the mixed-use development on Norodom Boulevard. As of 25 September 2026, the retail podium has reached 90% completion, while structural works continue to move upward across both ODOM Tower and ODOM Living.

Following the completion of the basement, the retail podium is now moving closer to becoming the project’s next major completed construction stage.

Meanwhile, ODOM Tower has progressed through the 4th Floor, while reinforcement works are underway at the 4th Floor of ODOM Living.

Overall project construction has now reached 18.30%, reflecting progress across the wider development as work continues on the two towers, shared retail podium, and other components of ODOM.

ODOM Construction Progress Update – September 2026

Construction at ODOM Phnom Penh continues to move forward across its residential, commercial, and shared podium components.

The latest ODOM construction progress highlights continued vertical development across both towers. At the same time, work on the shared podium has increased significantly since the previous update in June.

Current Construction Progress

Construction continues simultaneously across the development’s residential, commercial, and retail components.

The latest progress is particularly visible at the shared podium, which has advanced considerably since July. At the same time, both towers continue their vertical structural development.

Retail Podium Reaches 90% Completion

One of the most significant milestones in the September update is the progress of the retail podium, which has now reached 90% completion.

This represents a major increase from the 55% completion reported in July 2026.

The retail podium forms the shared base connecting ODOM Tower and ODOM Living. As a result, its progress represents an important construction milestone for the development as a whole.

With the basement already completed, the podium is now moving closer to becoming the next major completed stage of ODOM.

ODOM Tower Progresses Through the 4th Floor

Structural construction at ODOM Tower continues to move upward.

As of 25 September 2026, structural works have progressed through the 4th Floor, marking considerable vertical progress since the previous update.

In July, the commercial tower had completed its Ground Floor columns and core walls as well as the 1st Floor slab. Reinforcement was then underway for the next columns and core walls.

The latest milestone therefore shows continued advancement of the commercial component over the past two months.

ODOM Living Advances to the 4th Floor

Progress also continues at ODOM Living, the residential component of the development.

Reinforcement works are currently underway at the 4th Floor, following the structural progress achieved during the previous construction period.

In July, ODOM Living had completed concrete works through the 2nd Floor, while the 3rd Floor slab had been cast and reinforcement for its columns and core walls was underway.

With construction now advancing at the 4th Floor, the residential tower continues its vertical development above the shared podium.

Overall ODOM Construction Reaches 18.30%

As of 25 September 2026, overall construction at ODOM has reached 18.30%.

While the retail podium itself is already 90% complete, the overall percentage reflects the much broader scope of the entire development.

ODOM consists of a 45-storey commercial tower, a 30-storey residential tower, and a five-storey shared podium, meaning substantial vertical construction and subsequent building works remain ahead.

Therefore, the overall percentage should be viewed separately from the completion percentage of individual components such as the retail podium.

Vertical Construction Continues

Overall, the latest ODOM construction progress demonstrates steady advancement across the development.

Both towers have reached new structural stages. Meanwhile, more than half of the shared podium has been completed.

These milestones follow ODOM’s transition from foundation works into above-ground construction earlier in 2026. The development continues to move toward its planned 2027 completion.

Major Project Timeline

ODOM has achieved several important milestones throughout 2026. The project has progressed from foundational works to the vertical construction of its residential and commercial towers.

TimelineConstruction Milestone
April 2026Following foundational works, construction moved into the primary structure. Rebar fabrication, formwork assembly, setting-out works, and reinforcement for Ground Floor columns and core walls were underway.
June 2026ODOM Living completed structural concrete works for the Ground Floor and 1st Floor, along with the 2nd Floor slab. ODOM Tower completed its Ground Floor columns and core walls. The shared podium reached 37% completion.
July 2026ODOM Living progressed to the 3rd Floor, while ODOM Tower continued above-ground structural works. The shared podium reached 55% completion.
September 2026The retail podium reached 90% completion. ODOM Tower structural works progressed through the 4th Floor, while reinforcement works advanced at the 4th Floor of ODOM Living. Overall project construction reached 18.30%.

Project Details: Engineering a Vertical Village

Developed by Urban Living Solutions (ULS), ODOM is a major mixed-use development on Norodom Boulevard. The project combines residential, commercial, retail, and lifestyle spaces within one integrated community.

ODOM consists of a 45-storey commercial tower and a 30-storey residential tower. A five-storey ODOM Square podium connects the two towers.

  • Premium Residential Living: ODOM Living features 138 residences with one- to four-bedroom layouts. Unit sizes range from approximately 82 sqm to 272 sqm. The residences combine spacious layouts with a modern classic design and Hard Titles.
  • Grade-A Commercial Space: ODOM Tower provides approximately 41,167 sqm of strata-title office space. Its design incorporates “Sky Villages” and integrated green spaces. These features help introduce natural light and ventilation throughout the tower.
  • Sustainability & Infrastructure: ODOM targets LEED Gold certification and incorporates approximately 8,316 sqm of landscaped areas. The development also includes high-spec building infrastructure and 100% backup power.

Read more: Space, Quality, Design: The Real Reasons ODOM Commands a Premium Price

Strategic Location & Investment Value

ODOM occupies a prominent location along Norodom Boulevard in Tonle Bassac. The area is one of central Phnom Penh’s established residential and commercial districts.

From ODOM, residents can easily reach key destinations across central Phnom Penh. Nearby landmarks include Independence Monument, AEON Mall 1, the Royal Palace, embassies, and government institutions. The surrounding area also offers a wide selection of restaurants, cafés, shops, and other amenities.

In addition, ODOM combines residential, Grade-A office, retail, and lifestyle spaces within one development. This mixed-use concept creates an integrated environment for residents, businesses, and visitors.

ODOM Living has reported a presale rate of more than 50%. Residential units start from $290,648. Meanwhile, ODOM Tower offers office and commercial spaces starting from $227,251.

Urban Living Solutions has delivered six mixed-use projects in Cambodia. With its central location, sustainability focus, residential offering, and commercial spaces, ODOM represents another major addition to Phnom Penh’s property landscape.

Read more: Building for the Future: ODOM Phnom Penh Targets LEED® Gold Certification

Follow the Latest ODOM Construction Progress

The July 2026 milestones show continued progress across all major parts of the development. ODOM Living has reached the 3rd Floor, while ODOM Tower continues to rise above ground. In addition, the shared podium has now reached 55% completion.

IPS Cambodia will continue to follow the ODOM construction progress as the development moves toward its planned completion in 2027.